Question 6027 of 223 · California Water Treatment Operator Exam

A sedimentation basin with a surface area of 2,500 sq ft receives 1.0 MGD. What is the surface loading rate?

Exactly one answer is correct.

Show solution

Correct answer to question 6027

  • A: 400 gpd/sq ft

Explanation

Surface loading rate = 1,000,000 gpd / 2,500 sq ft = 400 gpd/sq ft.