Question 4022 of 229 · California Water Distribution Operator Exam

How far from the edge of an excavation should spoil piles and equipment be kept?

Exactly one answer is correct.

Show solution

Correct answer to question 4022

  • C: At least 2 feet

Explanation

Material too close to the edge can fall back into the trench or add load to the walls. Two feet is the minimum setback.