Question 8002 of 234 · California Wastewater Operator Exam
A wastewater treatment plant with a primary process and a design flow of 0.8 MGD is classified as
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 8002
- B: Class I
Explanation
23 CCR 3675 classifies primary plants of 1.0 MGD or less as Class I. A primary plant with design flow over 1.0 through 5.0 MGD is Class II.
More questions: Regulations, Classification and Operator Certification
- 8003A conventional treatment pond is classified as
- 8004An activated sludge plant with a design flow of 3.0 MGD is classified as
- 8005A biofiltration (trickling filter) plant with a design flow of 0.9 MGD is classified as
- 8006A primary treatment plant with a design flow of 3 MGD is classified as
- 8007What minimum grade must the chief plant operator hold at a Class II wastewater treatment plant?
- 8008What minimum grade must the designated operator-in-charge hold at a Class III wastewater treatment plant?