What should be done with wet or unstable soil at the bottom of a trench before laying pipe?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 5016
- D: Dewater and stabilize the bottom, and place bedding
Explanation
Pipe laid on soft soils settles and joints can fail. Dewatering pumps and bedding stone create a stable base.