Question 5009 of 229 · California Water Distribution Operator Exam
Who should be notified before a planned flushing program?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 5009
- C: Customers, the fire department and anyone affected by the flushing
Explanation
Notice prevents complaints and allows sensitive users to protect equipment. Discolored water after flushing is common.
More questions: Water Mains and Piping
- 5010What is a typical sign of a main break?
- 5011Which method is used to locate a buried metallic pipe?
- 5012What is the purpose of a tracer wire installed with plastic pipe?
- 5013How is a temporary service set up during a main repair?
- 5014Which practice prevents contamination of a pipe being installed?
- 5015What is the correct way to lower a heavy pipe section into a trench?